Thursday
January 16, 2025
- Lots of noise. Jack hammer noises. Large or multiple compressors running.
- Telehandler parked. Did not see in use.
- Large red dumpster on road.
- Portable crane removing debris from roof of Confederation Centre.
Wednesday
January 15, 2025
- Used a portable crane to remove debris from the roof of the Confederation Centre.
- Noise: Large or multiple compressors running.
- Lifted small amounts of debris from above Confederation Centre delivery bay with a medium sized telehandler.
- Delivered a dumpster. (This is louder than one might think.)
- Parking for contractors.
- Removed Debris - GFL large truck leaving Richmond via Queen.
- There is nothing happening near the Confederation Centre's box office. There aren't even cars parked there.
Monday
January 13, 2025
- Contractors have their pickup trucks parked on the street. There are three of them.
- The small excavator bucket on the north sidewalk is still there.
- Stack of concrete slabs still on brick patio.
Sunday
January 12, 2025
- No activity in the zone.
- The small excavator bucket on the north sidewalk is still there.
- Stack of concrete slabs still on brick patio.
Saturday
January 11, 2025
- There was no activity in the zone.
- The small excavator bucket on the north sidewalk is still there.
- Stack of concrete slabs still on brick patio.
Friday
January 10, 2025
- Not much happening onsite outside today.
- The white and red plastic corregated sign that read, "STREET CLOSED" has been replaced with new text: "STREET CLOSED TO TRAFFIC SIDEWALK OPEN"
- Large dumpster in front of stage doors still there. It may have moved by the end of the day as it was not there on Saturday morning.
- There was a pickup truck and trailor removing debris.
- There is a small excavator bucket on the north sidewalk.
- Stack of concrete slabs still on brick patio.
Thursday
January 9, 2025
- Large dumpster still in front of stage doors.
- Stack of concrete slabs still on brick patio.
Wednesday
January 8, 2025
- A large dumpster has been placed in front of the stage doors.
- Not much else has taken place all day.
- Stack of concrete slabs still on brick patio.
Tuesday
January 7, 2025
- A yellow temporary construction fence that appears to be able to be removed within a matter of hours was installed early in the morning.
- There is a white and red plastic corregated sign that reads, "STREET CLOSED"
- There are cars parked on the street and the east end of Richmond Street does not have a gate across.
- A mobile crane on a large flat bed truck removed debris from the roof of the Confederation Centre. The debris was lowered while cars still parked on the street.
- They took debris away in a trailor pulled by a pickup truck.
- Stack of concrete slabs still on brick patio.
Monday
January 6, 2025
- There are a few stacks of concrete just off the north sidewalk on the brick patio. It appears to be debris and not new usable material.